USACE Bathroom Lift
Tenant Improvements
Project Owner: General Services Administration
GSA Contract: 47PL0119P0061
Location: USACE Seattle District, Seattle, WA
Period of Performance: September 17, 2019 – Januaury 31, 2020
Contract Completion: $45,170.33
Project Scope:
- RJK Construction Managed and Provided All Drawings, Labor, Materials/Tools and Equipment to Install an ADA Bathroom Lift
- Provided All Electrical Work and Permitting Associated with the Installation of the Lift
- Engineered and Installed Surehands Bathroom Lift and a New Low Profile Wall-to-Wall Rail with Structural Blocking
- Patched Ceramic Wall Tile to Match Existing Wall
- Installed a Nema 5-20R Duplex Receptacle
- Interfaced with GSA and Subcontractors to Successfully Finish this Project On-Time and On-Budget