Timberline Lodge Sewage Treatment Plant Upgrades
Tenant Improvements
Project Owner: United States Forest Service
USFS Contract: 12046W20C0005
Location: Timberline Lodge, Clackamas County, OR
Period of Performance: June 8, 2020 – December 15, 2020
Contract Completion: $596,257.14
Project Scope:
-
RJK Construction Provided All Labor, Materials/Supplies and Equipment to Perform Various Upgrades to the Timberline Lodge Sewage Treatment Plant
-
Critical Shutdown to Replace Electrical Panels-Maximum Shutdown 2 Hour Limit
-
Designed Scaffolding for Work Performed Above Sewage Treatment Tank
-
Demolition and Removal of Existing Fans and Ductwork
-
Installed (2) Unit Heaters, Ductwork, (1) Supply Fan, Exhaust Fans, Control Dampers and Arctic Hoods and Seismic Bracing for Ductwork
-
Demolition and Removal of Existing Light Fixtures, Switches and Safe-Off of HVAC Equipment
-
Installed New LED Light Fixtures, Lighting Control, HVAC Equipment Power
-
Replaced Electrical Panels and Added Covers for CT Can and Meter
-
Installed Gas Detection System
-
Design Build Electrical Enclosure
-
Interfaced with USFS and Numerous Subcontractors