Project Owner: General Services Administration
GSA Contract: 47PL0120C0021
Location: Mark O. Hatfield Federal Courthouse & Edith Green Wendel Wyatt Courthouse, Portland, OR
Period of Performance: September 8, 2020 – July 21, 2020
Contract Completion: $994,492.35

 

Project Scope:

  • RJK Construction Provided All Labor, Materials and Equipment for the Repair and Replacement of Entrance Doors and Windows of the Mark O. Hatfield U.S. Courthouse
  • Work Completed During Continued Portland Civil Unrest
  • Restored Building Envelope, Physical Security and Aesthetics
  • Removed the Damaged Panels and Replaced Glazing for 5 Levels/Floors (69 Total)
  • Included Replacing the Glass Entry Doors, Embossed Sidelights and DoorHardware
  • Installed Right & Left-HandFloor Closers, Including a Concealed Floor Closer, and Added Door Bottom Arms for the Entry Doors
  • Applied Security/Anti-Graffiti Film on All New Glass Entry Doors and Windows on the 1stFloor Building Perimeter
  • Added Reflective Glass to the West Elevation of the Building
  • The Contract’s Original Scope of Work Evolved as the Hatfield Courthouse Experienced a Second Wave of Vandalism Resulting in Additional Change Orders and Extra Work Items Added to the Contract
  • Interfaced with GSA and Various Subcontractors